Feedback

Bayou Blue Assembly Of God Inc V Church Mutual Insurance Company Si

                UNITED STATES DISTRICT COURT                             
                EASTERN DISTRICT OF LOUISIANA                            


BAYOU BLUE ASSEMBLY OF                    CIVIL ACTION                   
GOD, INC.                                                                

VERSUS                                    NO: 23-6378                    


CHURCH MUTUAL INSURANCE                   SECTION: “J”(4)                
COMPANY, S.I.                                                            


                     ORDER AND REASONS                                   

    Before the Court are a Motion for Partial Summary Judgment Regarding 
Extra-Contractual  Claims  (Rec.  Doc.  17),  filed  by  Defendant  Church  Mutual 
Insurance Company, S.I., and an opposition filed by Plaintiff Bayou Blue Assembly 
of  God,  Inc.  (Rec.  Doc.  22),  to  which  Defendant  replies  (Rec.  Doc.  26).  Having 
considered the motion and legal memoranda, the record, and the applicable law, the 
Court finds that the motion should be GRANTED.                            
            FACTS AND PROCEDURAL BACKGROUND                              
    This case arises out of damage to Plaintiff’s property from Hurricane Ida. 
Insured  by  Defendant,  the  property  included  Plaintiff’s  church  and  thrift  store. 
Within a month of the storm, Defendant documented $476,670.98 in damage and, 
after applying policy deductibles, tendered timely payment. Disagreements between 
the  parties,  however,  had  already  developed,  with  Plaintiff  contending  that  the 
damage  assessment  was  inadequate  and  Defendant  countering  that  Plaintiff’s 
mitigation  efforts  had  morphed  into  widespread  property  demolition.  In  early 
November,  Plaintiff  submitted  demands  for  $1.4  million  related  to  tarping  and 
mitigation. Thereafter, Defendant revised its damage estimate to over $1 million and 
again tendered payment for that amount after deductible application. At the same 

time, Plaintiff made an additional demand of $2.19 million, which included estimates 
for  property  damage  and  mitigation  efforts;  Plaintiff,  however,  subsequently 
characterized  this  demand  as  “a  preliminary  estimate”  and  abandoned  it  as  a 
sufficient  proof  of  loss.  (Rec.  Doc.  17-7  at  276  ll.21–23  (deposition  of  Plaintiff 
representative)). Further complicating the accounting of Plaintiff’s demand, Big West 
Buildings Services originally invoiced Plaintiff $1,720,431.30 for mitigation work but 

later  accepted  $982,000  as  full  payment,  having  reduced  the  amount  due  to  a 
“gentleman’s agreement.” Id. at 143 ll.5–10, 144 l.25–145 l.1.            
    A month later, Defendant again revised its damage estimate to over $1.6 
million and tendered payment. Five months later, Plaintiff submitted to Defendant 
“a comprehensive evaluation of loss and replacement.” Id. at 287 ll.13–14. Totaling 
$4,993,121.62, the estimate valued church damages at $4,456,688.12 and thrift store 
damages at $476,433.50. Three months after the comprehensive estimate, however, 

Plaintiff sent Defendant a “build back” proposal for the church totaling $1,827,915. 
(Rec. Doc. 17-28). The August 2022 build back proposal was based on an estimate 
that predated the comprehensive evaluation by a month. In a series of letters that 
followed, Defendant requested more detailed costs in order to segregate out duplicate 
and uncovered demands: “We can[]not accept the proposal as satisfactory proof of loss 
as it is not itemized and appears to include the same disputed scope of repairs 
necessary as a result of the mitigation contractors unagreed and unsupported scope 
of demolition.” (Rec. Doc. 17-29 at 2 (Sept. 6, 2022 email to Plaintiff counsel)). With 
no additional payment tendered by Defendant,1 Plaintiff filed this action, raising 

claims of breach of insurance contract and for bad faith penalties.       
    Defendant now moves to dismiss the bad faith claim. Plaintiff opposes. 
                       LEGAL STANDARD                                    
    Summary judgment is appropriate when “the pleadings, the discovery and 
disclosure materials on file, and any affidavits show that there is no genuine issue as 
to any material fact and that the movant is entitled to judgment as a matter of law.” 

Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986) (citing Fed. R. Civ. P. 56); see Little 
v. Liquid Air Corp., 37 F.3d 1069, 1075 (5th Cir. 1994). When assessing whether a 
dispute as to any material fact exists, a court considers “all of the evidence in the 
record but refrains from making credibility determinations or weighing the evidence.” 
Delta & Pine Land Co. v. Nationwide Agribusiness Ins. Co., 530 F.3d 395, 398 (5th 
Cir. 2008). All reasonable inferences are drawn in favor of the nonmoving party, but 
a  party  cannot  defeat  summary  judgment  with  conclusory  allegations  or 

unsubstantiated assertions. Little, 37 F.3d at 1075. A court ultimately must be 
satisfied that “a reasonable jury could not return a verdict for the nonmoving party.” 
Delta, 530 F.3d at 399.                                                   



1 In January 2025, fifteen months after the commencement of this litigation and after an inspection of 
the  work,  Defendant  again  adjusted  its  damage  estimate,  finding  a  total  replacement  cost  of 
$1,697,418.98 and, after application of depreciation and deductible, issuing a total payment to Plaintiff 
of $1,583,431.61. (Rec. Doc. 17-4).                                       
    If the dispositive issue is one on which the nonmoving party will bear the 
burden of proof at trial, the moving party may satisfy its burden by merely pointing 
out that the evidence in the record is insufficient with respect to an essential element 

of the nonmoving party’s claim. See Celotex, 477 U.S. at 325. The burden then shifts 
to the nonmoving party, who must, by submitting or referring to evidence, set out 
specific facts showing that a genuine issue exists. See id. at 324. The nonmovant may 
not rest upon the pleadings but must identify specific facts that establish a genuine 
issue for trial. See id. at 325; Little, 37 F.3d at 1075.                 
                         DISCUSSION                                      

    Defendant argues that it cannot be found to have arbitrarily declined to pay 
all of Plaintiff’s damage demands because there are legitimate questions regarding 
the scope and causation of the loss. Louisiana’s insurance “bad faith” laws, codified 
in Louisiana Revised Statutes §§ 22:1892 and 22:1973, authorize recovery of bad faith 
penalties  from  insurers  who  fail  to  pay  legitimate  claims  in  a  manner  that  is 
arbitrary, capricious, or without probable cause. Spears v. State Farm Ins. Co., No. 
08-3183, 2009 WL 1674186, at *2 (E.D. La. June 12, 2009). “A party seeking relief 

under either statute has the burden of establishing three things: (1) the insurer 
received a satisfactory proof of loss; (2) the insurer failed to pay the claim within the 
applicable statutory period (thirty or sixty days); and (3) the insurer’s failure to pay 
the claim was arbitrary and capricious.” XL Specialty Ins. Co. v. Bollinger Shipyards, 
Inc., 954 F. Supp. 2d 440, 444 (E.D. La. 2013) (citing Dickerson v. Lexington Insurance 
Co., 556 F.3d 290, 297 (5th Cir. 2009)).                                  
    A refusal to pay is arbitrary, capricious, or without probable cause where the 
refusal was vexatious, unjustified, or without reasonable or probable cause or excuse. 
Dickerson, 556 F.3d at 300; Louisiana Bag Co. v. Audubon Indem. Co., 999 So. 2d 

1104, 1114 (La. 2008) (quoting Reed v. State Farm Auto. Ins. Co., 857 So.2d 1012, 
1021 (La. 2003)). Thus, bad faith should not be inferred when “there is a reasonable 
and legitimate question as to the extent and causation of a claim.” Reed, 857 So. 2d 
at 1021. The statutory penalties should only be imposed when the facts “negate 
probable cause for nonpayment,” and penalties are not imposed “when the insurer 
has a reasonable basis to defend the claim and acts in good-faith reliance on that 

defense.” Louisiana Bag Co., 999 So. 2d at 1114 (quoting Guillory v. Travelers Ins. 
Co., 294 So. 2d 215, 217 (La. 1974) and Reed, 857 So. 2d at 1021); see also Spears, 
2009 WL 1674186, at *2 (granting summary judgment on bad faith claim).    
    In this case, Plaintiff bears the burden of proving its claim for bad faith 
damages, including proving that Defendant’s refusal to tender further payments was 
arbitrary and capricious. Accordingly, on summary judgment, Defendant may satisfy 
its burden by pointing out that the evidence in the record is insufficient with respect 

to  the  arbitrary-and-capricious  element.  Defendant  argues  that,  because  of  the 
legitimate questions as to whether the alleged damage to Plaintiff’s property was 
caused by Hurricane Ida or by unnecessary or deficient work of Plaintiff’s contractor 
Big West, summary judgment on the bad faith claim is appropriate.         
    Plaintiff  does  not  deny  that  Big  West’s  mitigation  work  amounted  to 
widespread demolition of the church building. Instead, Plaintiff directs attention to 
a  “Water  Restoration  and  Mold  Remediation  Protocol”  issued  by  Defendant’s 
consultant three weeks after Hurricane Ida: “By Defendant’s Logic, Plaintiff should 
have waited 24 days after Hurricane Ida before it began mitigating it’s [sic] severely 

water[-]damaged buildings according only to JS Held’s protocols.” (Rec. Doc. 22 at 6). 
Plaintiff’s argument, however, misses the mark. The issue presented is not whether 
any  mitigation  should  have  occurred  but  whether  such  drastic  demolition  work 
presents a reasonable and legitimate basis for Defendant to question the mitigation 
and resulting rebuild. Plaintiff’s use of the “Water Restoration and Mold Remediation 
Protocol” drives home the point: only certain perimeter walls were marked for total 

removal. (Rec. Doc. 22-10). Plaintiff’s mitigation efforts and associated rebuilding in 
areas less affected by Hurricane Ida damage may ultimately present a covered claim, 
but Defendant’s refusal of payment cannot be described as vexatious, unjustified, or 
without reasonable or probable cause or excuse. See Dickerson, 556 F.3d at 300. 
    This conclusion is further supported by Plaintiff’s shifting damage amounts. 
In  November  2021,  Plaintiff  demanded  $2.19  million  for  property  damage  and 
mitigation  efforts,  but  later  abandoned  the  demand,  describing  it  as  only  “a 

preliminary estimate”. (Rec. Doc. 17-7 at 276 ll.21–23). Relatedly, Big West initially 
charged Plaintiff $1,720,431.30 for mitigation work but later accepted $982,000 as 
full payment, having reduced the amount due to a “gentleman’s agreement.” Id. at 
143 ll.5–10, 144 l.25–145 l.1. Plaintiff makes no effort to explain this discrepancy. 
Finally, Plaintiff offered “a comprehensive evaluation of loss and replacement[,]” 
totaling nearly $5 million. Three months later, however, Plaintiff demanded over $1.8 
million to build back the church, based on a proposal that predated—but was not 
included in—its comprehensive evaluation. Defendant repeatedly communicated its 
concern and confusion over the proposal, arising from Big West’s demolition work. 

    In  sum,  Defendant  reasonably  questioned  the  scope  and  causation  of  the 
claimed damage. Put another way, as it is Plaintiff’s burden to prove Defendant’s bad 
faith, Defendant has pointed to an insufficiency with respect to an essential element 
of Plaintiff’s claim, namely, that Defendant’s failure to pay the claim was arbitrary 
and capricious.                                                           
    Accordingly, the summary-judgment burden shifts to Plaintiff, who must set 

out  specific  facts  showing  that  a  genuine  issue  exists  that  Defendant  had  no 
reasonable basis for claim denial. Simply, Plaintiff fails to do so. Plaintiff attempts to 
justify certain repairs as necessary (HVAC) or as within the amount of replacement 
cost value (roof). Plaintiff may have additional claims deserving coverage, but such is 
not the issue before the Court. There are genuine issues over the coverage and 
causation of the property damage. Thus, Defendant’s withholding of further claim 
payment  is  reasonable,  not  vexatious.  In  turn,  the  bad  faith  claim  is  ripe  for 

summary-judgment resolution.                                              

                         CONCLUSION                                      
    Accordingly,                                                         
    IT  IS  HEREBY  ORDERED  that  Defendant  Church  Mutual  Insurance  
Company, S.I.’s Motion for Partial Summary Judgment Regarding Extra-Contractual 
Claims (Rec. Doc. 17) is GRANTED. 
     New Orleans, Louisiana, this 23rd day of July, 2025. 


                                         OK                       fale 
                                     _ JA\KA SAN [Ni  ( / 
                                   CARL J. BARBIFR   V 
                                   UNITED STATHS DISTRICT JUDGE